For the latest version of JMP Help, visit JMP.com/help.


Reliability and Survival Methods > Reliability Growth > Example Using the Reliability Growth Platform
Publication date: 11/10/2021

Example Using the Reliability Growth Platform

Suppose that you are testing a prototype for a new class of turbine engines. The testing program has been ongoing for over a year and has been through three phases.

The data are given in the TurbineEngineDesign1.jmp sample data table, found in the Reliability subfolder. For each failure that occurred, the number of days since test initiation was recorded in the column Day. The number of failures on a given day, or equivalently, the number of required fixes, was recorded in the column Fixes.

The first 100-day phase of the program was considered the initial testing phase. Failures were addressed with aggressive design changes, resulting in a substantially revised design. This was followed by another 100-day phase, during which failures in the revised design were addressed with design changes to subsystems. The third and final testing phase ran for 250 days. During this final phase, failures were addressed with local design changes.

Each phase of the testing was terminated based on the designated number of days, so that the phases are time terminated. Specifically, a given phase is time terminated at the start time of the next phase. However, the failure times are exact (not censored).

1. Select Help > Sample Data Library and open Reliability/TurbineEngineDesign1.jmp.

2. Select Analyze > Reliability and Survival > Reliability Growth.

3. On the Time to Event Format tab, select Day and click Time to Event.

4. Select Fixes and click Event Count.

5. Select Design Phase and click Phase.

6. Click OK.

The Reliability Growth report appears. The Cumulative Events plot shows the cumulative number of failures by day. Vertical dashed blue lines show the two transitions between the three phases.

Figure 10.2 Observed Data Report 

Observed Data Report

7. Click the Mean Time Between Failures disclosure icon.

This provides a plot with horizontal lines at the mean times between failures computed over intervals of a predetermined size. An option in the red triangle menu enables you to specify the interval size.

Figure 10.3 Mean Time between Failures Plot 

Mean Time between Failures Plot

8. Click the Duane Plot disclosure icon.

This provides a plot that displays the Cumulative MTBF estimates on the vertical axis versus the time to event variable on the horizontal axis. If the data follow the Crow-AMSAA model, the points should fall along a line when plotted on log-log paper.

Figure 10.4 Duane Plot 

Duane Plot

9. Click the Reliability Growth red triangle and select Fit Model > Piecewise Weibull NHPP.

This fits Weibull NHPP models to the three phases of the testing program, treating these phases as multiple stages of a single reliability growth program (Figure 10.5). Options in the Piecewise Weibull NHPP red triangle menu provide various other plots and reports.

Figure 10.5 Piecewise Weibull NHPP Report 

Piecewise Weibull NHPP Report

Want more information? Have questions? Get answers in the JMP User Community (community.jmp.com).